Clover Valley Lumber Co. #4

Restoration Work Log

08/13/11

Lynn, Les and Chris with several of the first cut sheets of new metal ready to have further holes and cuts made so they can be installed on the boiler.
08/13/11
Jeff tightening piping in the cab.
A lot of work is happening on the engineer's side.  Gerald insulating, Pam climbing back up with another bucket of mud and Henry in the cab doing some fabrication work.
08/13/11
Henry working on PLA's large sheet metal brake that will be used to fabricate the new jacket.
Gerald still hard at work, this time on the fireman's front door.
08/13/11
Gerald installing the last few pieces of insulation.
Pam "mudding" the belly insulation, a fun job as a good portion of the mud falls back down on you.  Pam is still smiling through it all.
07/30/11
Gerald at work insulating the firemans side.  Notice the buttstrap that will be insulated later with thinner material.
Top of the first course with insulation around the bell, dynamo bases and the buttstrap insulated with a thin layer of calcium silicate.  The rivit heads are not insulated.
07/16/11
Master Insulator Pam at work on the 3rd coarse - almost 3/4 of the way done with insulating.
Tom wire brushing one of the better looking pieces of material in a futile attempt to save some of the original material.  In the end, we decided that it is only good for a pattern.
07/16/11
Henry welding in additional cab floor supports to try to fix the "sagging cab floor" issue.

Number 999 of 1001 uses for a broom.  Gerald cleaning rust off a piece of the old jacket material.
07/16/11
Jeff looking though the old jacket material to see if any can be saved.  The sheet metal has done its job over the last 90 years but is severely corroded and needs to be replace.

CJ under the engine installing insulation.
07/16/11
Alan driving the Pettibone with another piece ready to go back on the #4.  This time, it's the dynamo.

Gerald positioning the dynamo to install the mounting bolts.
07/16/11
The Mallet outside waiting for more parts in the early morning mist which seemed more like another day of rain.  This is July, correct?
Gerald, Tom and Jeff mounting the bell yoke back on the boiler.
07/16/11
Jim doing a little painting on the sand dome.

Pam and Jeff place the sand dome back on the boiler in preparation for insulation.
07/09/11
Why does it seem that Pam is always found under the locomotive?  Probably because it requires someone smaller and Charlie is out of town.  As before, Jim is busy custom cutting the blocks for Pam to install.
07/09/11
Alan is busy installing wrapping around the lubricator lines.  The wrapping will keep the lines from abrading against the boiler shell.
07/09/11
There is always something else to work on.  This time, it is the sand dome.  The base is rebuilt and ready to go back on.

Gerold is expressing is delight at lagging a boiler on this bright, sunny day.
07/02/11
CJ working on the upper portion of coarse #2.  Nearly half done!
Les and Chris installing new air piping between the new air tanks.
07/02/11

Pam insulating the belly of the beast.
Pam and Jim at work.
06/25/18

Master carpenter Henry trying his cutting skills on calcium silicate insulation instead of lumber.
06/25/11
Dave and Gerald running wire around the boiler which will hold the block insulation  during installation.
Pam setting block insulation near the top of the boiler.  The first coarse is almost done, 3 more to go.
06/18/11
Henry making some "fine" adjustments in preparation for some piping repair.
Gerald and Henry tightening up a leaky injector line pipe.
06/17/11

We now have a reinstalled and properly working coupler.
06/17/11
Johnathon at work prepping bolts for reinstallation of the rear coupler pocket.  The pocket is not original to this engine.
When Clover Valley installed it, they did a really poor job.
Johnathon tightening the pocket mounting bolts.
06/12/11

Always look out for flying brick when brickwork is in progress.
06/11/11
Jeff Waiting with the masonry saw, ready for the next brick to cut.  The keyhole firebox on the #4 required a lot of brick cutting and fitting.
Gerald setting the flash wall brick.
06/04/11

Henry and Gerald working on piping in one of the many tight spaces on the #4.
06/04/11
Not a lot of progress on the brickwork but it looks like everything is ready to go - just need someone to fill those gloves and start working.
Dave discovers the reason for the lack of progress - Gerald has not had enough coffee yet.
06/04/11
Gerald and Alan take a break from bricking.  It was a rainy day outside but they missed the bad weather, spending 5 hours inside the confines of the firebox.
Mixing another bucket of firebrick mortar.
05/14/11
A good steam test today on the Clover Valley #4.  We found a few things we need to fix such as valves that need to be relapped, some leaky flexible caps that did not leak under a hydro and leaky piping but overall we were all smiles after the day.  Thank goodness this hurdle is over, on to finishing the locomotive to put her back in service.
05/14/11

Jeff's thumbs up says it all.
04/16/11
Pam insulating the air compressor steam feed line.

Test fitting the new builders plates donated by George Lavacot. They will look great once we permanently mount them.

04/16/11

Jeff showing Gerald how to lap the throttle.

One scary group of volunteers!
04/09/11
Errol taking it easy on a "comfortable" folding chair while supervising.  It is good to have him back , we have missed him.
Jeff (who volunteers at the Orange Empire Railway Museum) spending a few hours of his northern California visit.
04/09/11
A bunch of help involved in mounting the air tank on the engineer's side.  Pam, Henry (on the lift), Scott and Chris.

A group volunteer photo for April 9th.  Henry, Jeff, Scott, Chris, Alan and Pam behind the camera.
04/09/11

Front end work with Scott and Jeff.

Pam painting the piping in the cab.
04/09/11
Final picture  of the newly repaired smokebox, new petticoat and blower ring before the smokebox front is installed.
Pam and Scott preparing the front end for the smokebox front to be installed.
04/09/11

Pam and Scott guide the front end into place.

Jeff watches while Chris and Scott muscle the front end.
04/09/11
Henry tightening his new air tank bracket built for the fireman's side air tank.  The new bracket is mounted off of a cab support rather than from the cab floor which cause it to sag.
Completed and painted front end.
03/26/11

Charlie was caught dressing up the superheater plate.
03/26/11

Finally, the new blower ring and petticoat were installed.
03/26/11

While Alan was busy getting his hand stuck in the #4's throttle, Henry fabricates a new air tank bracket.
02/26/11
Charlie, Gerald and CJ reinstalling the power reverse.  Considering the difficulty we had taking it off the #4, this was a welcome easy job and the bolts almost slid into place.
02/26/11

Number 4 basking in the February sun.
02/26/11

Dave doing some final cleanup on the power revers guides.
Scott, Gerald and Charlie rigging up the power reverse.
02/26/11
A couple wees work by Henry, Jeff, Joe, Jim and others resulted in a rebuilt petticoat and new adjusting brackets.
Jim and Henry mounting the petticoat in the smokebox.

02/19/11
Our blacksmith Joe Mann made new adjusting brackets for the petticoat.  The old ones were welded into the smokebox and adjustment was impossible.
02/12/11

There is no better way to force work to be completed than locking Alan in the firebox until he finishes the Form 4 Documentation.
02/12/11

C.J. and Johnathon making a new air gauge support.
Charlie changing the brake valve on our SP boxcar in preparation for the March 13th Photographers Special.
02/12/11

Scott cleans and paints the air pump bracket.
Charlie and Jim finish painting  the power reverse.  In the background, Henry and Jeff work on making new brackets for the petticoat.

02/05/11

Another project completed - the superheaters all reinstalled and tightened.
02/05/11

Gerald and Pam work on cleaning all the caked grease and grime off the power reverse.
Chris and Les working on piping in the cab.
01/29/11

We removed the old air pump plumbing from th top of the smokebox and were able to get the last row of superheater elements installed.

01/29/11

The backhead shelf was painted and then installed in addition to finishing the piping for the whistle.
01/22/11

Jim, Pam and Henry working on the superheater units.
Dave Loyola inside the smokebox installing additional sealer around the branch pipe packing.
01/22/11

Henry carefully applies a new superheater clamp to the tube bundle to replace one of the old burned and rested clamps.
A newly installed clamp ready for welding.
01/22/11

Henry welds the clamp together.
Alan and Errol tightening up the first row of superheater units.
01/15/11
Pam lapping the superheater ball joints which fit into the header.  A tight lapped metal to metal joint is necessary on all 36 joints to prevent steam from leaking into the smokebox.
C.J., Scott and Charlie in the smokebox muscle a 15' superheater unit into the smokebox.
01/15/11

Jeff "The Inspector" is on site in the smokebox to check Charlie's work.
Charlie Lapping the superheater header in preparation for superheater installation.
01/15/11

Henry and Jeff installing the flexible exhaust joint from the low pressure cylinders to the nozzle in the smokebox.,
Pam, Jeff and Henry (hidden in the background) finishing the nozzle installation.

01/08/11

Henry with the reassembled spring and snap ring positioned in the press.  Johnathon thinks he can provide help with that dinkey sledge when we are using a 50 ton press.  Maybe he should get a bigger hammer!!
01/08/11
Gerald working rebuilding the injector for the engineer's side of the locomotive.

The cleaned underside of the nozzle.  The spring pack fits against the inner flat surface and the exhaust pipe seals into the center hole that leads to the nozzle.
01/08/11
The spring pack after about 4 hours of Henry cleaning the nozzle casting to get the pack out.
Pam making new gaskets.  It sure would be easier if we could just purchase them.

01/08/11
Scott Martel removing the brake cylinder lids in preparation for installing new brake cups.  Another one of the locations that are difficult to get to on compact locomotives.
Chris and Les working on the brake stand plumbing in the ca
b.
01/08/11

Henry starts cleaning the interior of the exhaust nozzle / flexible steam pipe joint.
Pam cleaning the exhaust pipe between the smokebox and front cylinders.  Not a great place to work at all.
01/08/11

Henry starts cleaning the interior of the exhaust nozzle / flexible steam pipe joint.

12/28/10

Johnathon was found under the engine working on the blowdown valve.
Henry working in the smokebox.  The liner is almost welded in place.  Next will come the nozzle.
12/28/10

Jeff happily cutting fire brick for Alan.
Alan installing fire brick in the pan.
Completed brickwork at the end of the night
.
12/11/10

Henry welding a bracket for the air brake system.
12/11/10
Chris working on making a new steam supply pipe for the engineer's side injector.  All the steam piping in the cab will be replaced by the time we finish.
Pam wrapping a steam pipe with insulation.
12/11/10
Pam, Jim, Chris and Henry taking a break while installing the smokebox liner.  There are only a few more feet to go.
Jim, Henry and Chris admire the installed liner.  Now comes a bunch of welding and bolting to tie the plate down in the smokebox.
11/27/10
Jim painting running gear.

Henry grinding on a new bracket.
11/20/10

The beginning of the brick work in the fire pan.
The great mason reaching out of  the job site.
10/30/2010

Backhead looking better every workday with piping and appurtances being added.
10/30/2010
Wait, wait!  Not quite ready yet.  This is never a good sight when inside the firebox caulking stays.

Henry Chandler finishing up on smokebox repairs.
10/30/2010

240 pounds of hydrostatic pressure on the gauge!!

Kruger looking for leaks with the hydro pump in the foreground.
10/30/2010
The mad plumber has moved from the Pettibone to the cab of the number 4.
Wild West at Brightside.
 Gerald holding Jim up with an injector mock up made to arrange brackets and piping.

10/30/3010
Les running running new piping in the tight confines under the engine.

Chris working on piping under the cab floor.

10/30/2010
Johnathon working on the pettibone brakes.

You can never have enough vice grips!  Jim showing off his paint brush extender tool.
10/23/2010

Some of the new firing piping running under the new firepan floor.

10/23/2010

Jeff and Charlie hydro testing more superheater units.
10/23/2010
Johnathon firing the water heater.  Using the #2 to heat water in the #4 in preparation for the hydro test.
Gerald and Jim working on the fireman's side injector.
10/23/2010
Jeff and Charlie hydro testing superheater units.
Henry burning some more rod.. The amount of welding done during the smokebox repair
is amazing.  We should have bought welding rod by the case.
10/02/2010
Backhead piping in progress, with most of the new firing manifold piping complete.  It is amazing how much time has been spent laying out and installing this piping.  Some of those involved include Les Fisher, Johnathon Kruger, Chris Holombo, Pam Cravens and Alan Siegwarth.
10/02/2010
Always time to answer the phone, despite the dirt.

Gerald and Jim cutting metal to be used in repainting the cab.
10/02/2010
Henry Chandler working on smokebox repairs.

Scott Martel doing a little metal cleaning on the running gear.
09/18/2010

Replacement of the bottom smokebox sheet is almost complete.  The outer shell is installed and welded into place.
04/26/2010
Jeff grinding the rear tube sheet preparing for tube installation.  Henry is on the right, removing a stay.
Closeup of Henry burning out an old staybolt.
04/26/2010
New Member Jim wire brushing one of the many tank support brackets.
Les working removing plumbing from the blowdown valve.
One more replacement stay to go in the boiler blackhead.
04/17/2010
Pam and Gerald threading staybolt on the engineers side of the cab.
John tirelessly wiring brushing the frame and running gear to remove all the rust, caked grease and dirt built up over many years of service.  Not a glamorous job, but thanks to John the engine will look much better when it returns to service.
04/17/2010
Another not so glamorous job, Jim is wire brushing the tank support brackets in preparation for painting.

Tapping another staybolt hole.
04/17/2010
Gerald and Pam continue working on staybolts on the engineers side of the cab.

Pam threading in a new flexible staybolt.
04/17/2010
Henry threading blackhead stays.  The second tap sticking out of the sheet is being driven by Pam in the firebox.
Gerald cleaning up stay threads with a die. 
Tapping stays two at a time. 
04/10/2010
Chris rethreading the side tank support bracket mounting holes on the boiler.

Henry tapping the holes in one of the new flush patches installed in the firebox in preparation for installing  new staybolts.
04/10/2010
C.J. painting one of the many tank support brackets.
Gerald is cleaning the threads on PLA's stock of staybolts.  Many of these stays will be used in the $4 but those that are not will be checked for size, cleaned, cosmolined and stored properly for use in the future.
04/10/2010
Alan threading in a new flexible staybolt.  (David Loyola photo)

Two new flexible staybolts installed, two more to go in this area of the firebox.
04/10/2010
Henry in the firebox working on tapping staybolt holes.
Jim (or at least his hands) threading a new rigid staybolt into place on the engineer's side sheet from outside the cab.  Great place to work - right next to the cab floor and wall.  The power reverse and other linkage had to be removed for this work.
1/23/2010
Completed tube sheet installation after riveting and welding.

One of the completed firebox flush patches in the firebox.
1/23/2010
Blake backing rivets with Johnathon Kruger providing added force by pushing on Blake's arms.
John with Dave adding weight riveting another one.  Doug stands by to tell the backing crew how the process is going.
1/23/2010
Blake backing a hot rivet underneath the boiler.  Down below, Johnathon Kruger is helping by pushing on Blake's arms to back the riveting.
Using tongs to handle the hot rivet, Henry Chandler puts a rivet in the hole while Blake waits to start backing with a 90 pound gun.
1/23/2010
Rivet being heated until white hot in the rivet oven.
Dave Loyola and Doug Vanderlee listen as John Rimmasch explains the top side riveting procedure.  Dave will help John by adding weight on John's shoulder to keep the air gun down.  Doug will communicate with the rivet heating crew.
1/23/2010
The lower portion of the front tube sheet had to be removed had reduced the thickness of the knuckle below safe levels.
Wasatch Railroad Contractors welder Blake welding up cab wear on the rear door sheet.
12/12/09

The new section of cab wall formed and fitted but yet receive the holes necessary for the appurtenances that have to pass through it.
12/12/09

Henry drilling holes in stay bolts that will be removed from the blackhead.
The new Mallet house.  The number 4 sitting inside the completed tent which was finished just in time as it as been raining continuously here in the Bay Area.
12/12/09

Les cleaning the plate cut out to replace the engineers lower cab wall.
Chris drill mounting holes for the new fire pan.
11/19/09
Not a common sight when you look through the firebox door - the ground!  The bar across the opening is actually the axle on the rear driver.  The fireman is in the process of being cut out and replaced as it has been modified beyond believe over the years of service on the Clover Valley.  Actually, we are in the process of cutting out TWO firebox pans as the lumber company just added another floor over the old one (with an one inch area in between filled with Bunker C!) when it was time to repair the firepan. 
11/19/09
Gerald DeWitt and Dan Dornbrach installing cable stays to tighten up and square the tent support structure.
End of the day, the Mallet is backed down into the new structure for the night.  Hopefully just one more day to finish the tent installation so the engine will inside protected from the weather all winter.
11/19/09
When all else fails - READ THE DIRECTIONS.  Dan, Jim, Henry and Gerald demonstrate this long lost art.
There is sure a lot of this reading directions stuff today.  Johnathon and Charlie in action.
11/19/09
Henry, Pam and Gerald lay out one of the tent support hoops.

Pam, Dave Loyola, Henry Chandler and Gerald DeWitt raise up one of the tent supports after assembly.
10/31/09
No better way to move material than shovels.  Alan Siegwarth spreading asphalt chips.
Nice picture of the new improved walkway/work area with asphalt chips spread out and compacted alongside the track.  Once the tent is complete, it will almost be as nice as working inside the shop.
10/31/09
Dumping asphalt chips to use as a raised walkway inside the tent using one of the PLA's recently acquired Central California Traction ballast cars.
Henry Chandler, Johnathon Kruger, Jim Adams and Dan Dornbrach take a break from shoveling.
09/26/09
Jeff and Gerald DeWitt reinstalling the firemans side cab step.  The bolts holding the steps on were rusted and corroded to the point that the step was no longer safe for use.  A simple job right?  No, of course not.  The repair required removing the step/welds, fixing and straightening the bent step, cutting and repairing the cab floor, building a doubler plate to support the step and finally - shown here - reinstalling the step.
09/26/09
Henry Chandler and Jeff Schwab making fine adjustments on the Mallet's cab.  All that is required is a little heat and a large sledgehammer.  Cab damage is being repaired in preparation for reinstalling the steps on the fireman's side.


09/12/09
Chris drilling out staybolt telltale holes inside the firebox.  Another long tedious job that requires patience because their is always the potential to cause a bigger problem if one of the drills breaks in a stay.    A lot of work happening on the engineers side of the locomotive.  Jeff and Dan discussing piping that needs to be replaced.  In the background, Henry and Les are working on cab repairs. 
09/12/09

Les drilling and fitting new angle to support the cab floor.  Years of exposure to the weather has rusted out sections of the cab that are being rebuilt for safety. 
09/12/09
Jim wire brushing and priming the saddle tanks.  Dan painting (after wire brushing and priming) one of the air tank supports on the firemans side of the locomotive.  The entire locomotive needs to be cleaned and repainted which Dan has graciously started - there is a lot to paint!
  Alan Siegwarth  Photos
09/12/09
Loading bridge timbers at a PLA storage yard in preparation to erect the new Mallet house - a tent building purchased to keep the engine dry through the winter.  The steam department is preparing to install the tent but needs to complete the unfinished shop track work including ballasting and lining the tracks before the tent can be installed.  Hopefully we have another dry month to complete the installation. 
Photograph by Alan Siegwarth

09/12/09
Henry crawling along the bottom of the boiler barrel after spending a morning cleaning inside the boiler.  This is a fun experience crawling along under the superheater flues - volunteers always accepted = )
08/29/09
Based on Jeff's smile, this picture must have been taken before he entered the boiler.  After a few hours crawling in the confined space of the boiler, volunteers coming out seldom have big smiles on their faces.  Gerald removing the fireman's side cab steps that need straightening.  Logging service was not easy on the step as it has hit numerous things along the right of way in its 30 years of service with the Clover Valley Lumber Company.
08/29/09
Henry working on washing the boiler to remove additional scale.  As usual with all PLA projects, the fire truck had to be repaired before this work could begin so the high pressure/flow PTO driven fire pump could be used in boiler washing.  The use of the fire truck made a difficult project much easier.  To the right of Henry, Gerald continues to work on removing the step.
08/29/09
Pamela Cravens packing flexible staybolt caps and sleeves with a nasty, grimy mix of graphite and oil. The graphite and oil mix keeps the flexible ball joint lubricated allowing the stay to move with boiler expansion and contraction.  Pam is shown reinstalling caps after months of work removing caps, cleaning the interiors and retapping the sleeve threads.  
08/29/09
Thanks to member donations to purchase parts and PLA volunteers like Pam, all the flexible staybolts that do not need repairing have been repacked with graphite and new gasket and cap installed. 

Alan Siegwarth Photo

08/07/09

Henry Chandler removes the last of the flexible staybolt caps on the blackhead in the cab.

Alan Siegwarth Photo
08/07/09
Engineers side boiler support plate remounted on the boiler after repairs.

Jeff Schwab working on cleaning, removing caps on the lower blackhead - hiding in between the frame under the cab floor.

Alan Siegwarth Photos
05/30/09
Painting and more painting.  Alan painting the wrapper sheet in the cab.
Henry using a little heat treatment to persuade rusty nuts off of the frame on the fireman's side of the engine.
05/30/09
Doug Vanderlee cleaning dirt and grease from the high pressure cylinder crosshead.
Les, Gerald and John working on the dirty job of graphiting and reinstalling flexible staybolt caps with new gaskets.
05/02/09

Les working in great conditions.
New caps and studs installed.
Alan Siegwarth Photos
05/02/09
Henry removing flexible staybolt caps for inspection.
Chris and Les show the extreme dexterity required to remove the throat sheet flexible staybolt caps.
Alan Siegwarth Photos
05/02/09
Dave and Les working on the rear furnace bearer plates.
Jeff installing new recessed flexible staybolt caps.
 
Alan Siegwarth Photos
05/02/09
Amazing what you get to work on in the name of keeping steam running.  Gerald and Al work on a PLA diesel welder, one nice machine.

Alan Siegwarth Photos.
02/07/09

Pettibone in place ready to remove power reverse.
Jeff, Henry and Harrison Hollidge work on removing power reverse bolts
02/07/09

Air pump being removed in preparation for smokebox repairs
741:  Dave Burla lifting the power reverse into a boxcar for storage.  Henry Chandler and Paul Hollidge assist.
01/17/09
Henry using an air chisel to help remove flexible stay bolt caps.  It is evident that these were not inspected very often and many of the cabs/sleeves need repair or replacement.
Alan Siegwarth Photo
01/17/09
Jeff drilling out staybolt tell-tale holes inside the firebox.  Photo taken through a hole in the rear tube sheet.
Gerald and David repairing the worn and bent rear boiler support bracket.
Alan Siegwarth Photos
01/13/09
Charles Franz taking ultrasonic readings on the boiler.
Cab wall cut away to get access to stay bolts.
Several thin spots cut out of fire box wall.
H P Wise Photos
01/10/09
Gerald and Jeff removing boiler piping while Charlie and Chris remove the firemans side air tank for access to UT test and remove the flexible staybolt caps on the boiler.

Alan Siegwarth Photo
01/10/09
Henry washing and more washing the boiler.  What a mess!
Alan, Jeff planning on how to do firepan work.

01/10/09
Jeff and Charlie machining a brake shoe head for the Mallet in the shop.

Gerald heating up the nuts holding the fireman's side support plate on the boiler.

Alan Siegwarth Photo
01/10/09
Alan demonstrates perfectly why the Mallet is so much fun to work on climbing over the low pressure steam delivery pipes to exit from under the boiler.  Baldwin built a compact, efficient locomotive but it is hard to get into to for maintenance and just as difficult to get out.  
Dave Loyola Photo
01/08/09
Picture of today's contract work on the Mallet front tube sheet.  The tube sheet came out really easy.  Notice the nice easy access to the bottom of the boiler now - no worry about taking some of the superheater tubes out now for access to the belly. 
A. Siegwarth Photo
12/23/08
The rear engine's center drive was repaired by the SP at Sacramento in 1936.  They left the proof in a stamping on the end of pin that says, "SAC 3.3.36", "TON 125" (the pressure need to press the pin in the wheel" and "R6 AXEL STEEL".
HP Wise Photo.
12/20/08

Removing the throttle.  Henry Chandler steadies the casting while Johnathon operates the forklift.

A Siegwarth Photo
12/20/08

Alan Siegwarth working in the confines of the steam dome to get the throttle
ready to remove.
Henry Chandler Photos
11/29/08

Henry Chandler working in the smokebox pulling tubes.

A Siegwarth Photo
11/29/08

Al and John putting a protective coating on the bare boiler.

A Siegwarth Photos
11/22/08

Chris Holombo, Les Fisher and Henry Chandler (out of sight in the smokebox) pull tubes out of the locomotive. 
A Siegwarth Photo
11/22/08

Les Fisher working on the cab floor while Kevin Zimmerman is painting the boiler.

 A Siegwarth Photo 
11/22/08

Alan Siegwarth priming the firebox wrapper sheet

Johnathon Kruger Photo
10/18/08

Henry Chandler and Gerald DeWitt removing tubes.

Patrice Warren Photo
08/31/08

Carefully machining the weld/bead off of the tubes.

A Siegwarth Photo
08/31/08
Charlie and Jeff in the firebox with a tube cutter installed and ready to cut the seal weld and bead from the rear tube sheet.   Removing the weld and bead will allow the tube to be pushed out of the sheet from the firebox end.
A Siegwarth Photo


Now that the forklift is in place, how were we going to get this tank off again?  Chris Holombo, Henry Chandler and Johnathon Kruger discuss rigging the tank to the forklift.


Happy operator now that Pettibone is in place between the #4 and passenger cars stored on yard track #1
06/14/08

Pettibone forklift maneuvered into tight quarters ready to lift the side tank off of the locomotive. 

A Siegwarth photo
06/14/08

Henry Chandler removing tank mounting bolts in preparation for removing the firemans side tank. 

A Siegwarth Photo
05/31/08

Chris Holombo, Les Fisher, Henry Chandler removing lots piping to get access to remove the Mallets side tanks.
09/29/07

A proud cleaning crew - Chris Holombo, Gerald DeWitt, Dave Loyola, Charles Franz, Jeff Schwab and Alan Siegwarth
09/27/07

Cleaning scale out of boiler.  Chemicals were added to the boiler and water heated to boiling point for improved scale removal.  Notice the steam coming out of the open steam dome which was left uncovered to prevent pressure buildup in the boiler.

Return To Main Page