12/28/10
Johnathon was found under the engine working on the blowdown valve. Henry working in the smokebox. The liner is almost welded in place. Next will come the nozzle. |
12/28/10
Jeff happily cutting fire brick for Alan. Alan installing fire brick in the pan. Completed brickwork at the end of the night.
|
12/11/10
Henry welding a bracket for the air brake system. |
12/11/10 Chris
working on making a new steam supply pipe for the engineer's side
injector. All the steam piping in the cab will be replaced by the
time we finish. Pam wrapping a steam pipe with insulation. |
12/11/10 Pam, Jim, Chris and Henry taking a break while installing the smokebox liner. There are only a few more feet to go. Jim,
Henry and Chris admire the installed liner. Now comes a bunch of
welding and bolting to tie the plate down in the smokebox. |
11/27/10 Jim painting running gear.
Henry grinding on a new bracket. |
11/20/10
The beginning of the brick work in the fire pan. The great mason reaching out of the job site. |
10/30/2010
Backhead looking better every workday with piping and appurtances being added. |
10/30/2010 Wait, wait! Not quite ready yet. This is never a good sight when inside the firebox caulking stays.
Henry Chandler finishing up on smokebox repairs. |
10/30/2010
240 pounds of hydrostatic pressure on the gauge!!
Kruger looking for leaks with the hydro pump in the foreground. |
10/30/2010 The mad plumber has moved from the Pettibone to the cab of the number 4. Wild West at Brightside. Gerald holding Jim up with an injector mock up made to arrange brackets and piping.
|
10/30/3010 Les running running new piping in the tight confines under the engine.
Chris working on piping under the cab floor.
|
10/30/2010 Johnathon working on the pettibone brakes.
You can never have enough vice grips! Jim showing off his paint brush extender tool. |
10/23/2010
Some of the new firing piping running under the new firepan floor.
|
10/23/2010
Jeff and Charlie hydro testing more superheater units.
|
10/23/2010 Johnathon firing the water heater. Using the #2 to heat water in the #4 in preparation for the hydro test. Gerald and Jim working on the fireman's side injector. |
10/23/2010 Jeff and Charlie hydro testing superheater units. Henry
burning some more rod.. The amount of welding done during the smokebox
repair is amazing. We should have bought welding rod by the case. |
10/02/2010 Backhead
piping in progress, with most of the new firing manifold piping
complete. It is amazing how much time has been spent laying out
and installing this piping. Some of those involved include Les
Fisher, Johnathon Kruger, Chris Holombo, Pam Cravens and Alan Siegwarth.
|
10/02/2010 Always time to answer the phone, despite the dirt.
Gerald and Jim cutting metal to be used in repainting the cab. |
10/02/2010 Henry Chandler working on smokebox repairs.
Scott Martel doing a little metal cleaning on the running gear. |
09/18/2010
Replacement of the bottom smokebox sheet is almost complete. The outer shell is installed and welded into place. |
04/26/2010 Jeff grinding the rear tube sheet preparing for tube installation. Henry is on the right, removing a stay. Closeup of Henry burning out an old staybolt. |
04/26/2010 New Member Jim wire brushing one of the many tank support brackets. Les working removing plumbing from the blowdown valve. One more replacement stay to go in the boiler blackhead. |
04/17/2010 Pam and Gerald threading staybolt on the engineers side of the cab. John tirelessly wiring brushing the frame and running gear to
remove all the rust, caked grease and dirt built up over many years of
service. Not a glamorous job, but thanks to John the engine will look
much better when it returns to service. |
04/17/2010 Another not so glamorous job, Jim is wire brushing the tank support brackets in preparation for painting.
Tapping another staybolt hole. |
04/17/2010 Gerald and Pam continue working on staybolts on the engineers side of the cab.
Pam threading in a new flexible staybolt. |
04/17/2010 Henry threading blackhead stays. The second tap sticking out of the sheet is being driven by Pam in the firebox.
Gerald cleaning up stay threads with a die.
Tapping stays two at a time. |
04/10/2010 Chris rethreading the side tank support bracket mounting holes on the boiler.
Henry
tapping the holes in one of the new flush patches installed in the
firebox in preparation for installing new staybolts. |
04/10/2010 C.J. painting one of the many tank support brackets. Gerald
is cleaning the threads on PLA's stock of staybolts. Many of
these stays will be used in the $4 but those that are not will be
checked for size, cleaned, cosmolined and stored properly for use in
the future. |
04/10/2010 Alan threading in a new flexible staybolt. (David Loyola photo)
Two new flexible staybolts installed, two more to go in this area of the firebox. |
04/10/2010 Henry in the firebox working on tapping staybolt holes. Jim
(or at least his hands) threading a new rigid staybolt into place on
the engineer's side sheet from outside the cab. Great place to
work - right next to the cab floor and wall. The power reverse
and other linkage had to be removed for this work. |
1/23/2010 Completed tube sheet installation after riveting and welding.
One of the completed firebox flush patches in the firebox. |
1/23/2010 Blake backing rivets with Johnathon Kruger providing added force by pushing on Blake's arms. John with Dave adding weight riveting another one. Doug stands by to tell the backing crew how the process is going. |
1/23/2010 Blake
backing a hot rivet underneath the boiler. Down below, Johnathon
Kruger is helping by pushing on Blake's arms to back the riveting. Using
tongs to handle the hot rivet, Henry Chandler puts a rivet in the hole
while Blake waits to start backing with a 90 pound gun. |
1/23/2010 Rivet being heated until white hot in the rivet oven. Dave
Loyola and Doug Vanderlee listen as John Rimmasch explains the top side
riveting procedure. Dave will help John by adding weight on
John's shoulder to keep the air gun down. Doug will communicate
with the rivet heating crew. |
1/23/2010 The lower portion of the front tube sheet had to be removed had reduced the thickness of the knuckle below safe levels. Wasatch Railroad Contractors welder Blake welding up cab wear on the rear door sheet. |